Let’s compare both available options with summarized information
proposed for these options:
Option 1: Direct Alignment
|
Option 2: Skirting Alignment
|
|
1.
Length of Impact
|
2km tunnel below the CCNR
|
9km under homes and businesses
|
2.
Depth of tunnel
|
40m Deep
|
Unknown
|
3.
Presence of physical structures
|
No Physical Structures
|
Supporting Ventilation facilities at the surface level
|
Perhaps, one can deduce that the depth of tunnel in Option 1
is 40m, was proposed such that the CCNR is 40m away from the tunneling works
and the drone of vibration from the moving trains, based on the RPZ.
The question is: Is
applying the RPZ to the CCNR adequate?
Or should we be looking at the RSZ, which is 60m?
Another site shed some light of concerns within the
RSZ:
On the same site, the following excerpt shows that there is
still some impact for such items to be considered restricted activities:
Option 2 does not clarify the depth of tunneling works, so
let’s assume that the depth is simply 20m, let’s look at the impact of
applying the RSZ to the CCNR:
Option 1:
And translating the above section to plan, we see the impact
of both options applying the RSZ:
Humus; Topsoil; Eluviation Layer; Subsoil; Regolith; Hard
Bedrock
Perhaps then, a third option could be further studied and considered. Let’s
say, hypothetically, the RSZ needs to avoid the subsoil layer as this layer may
contain the deepest roots of some trees, and the subsoil layer may be say 10m,
these will require tunnel works for both options to be deeper at say 75m both
schemes to have minimal impact.
And what would Option 3 cost?
Would the entire 50km length need to be deepened, affecting all station depths?
Or could this depth also serve other functions such as civil defence shelters or even connect to the various underground rock caverns where Singapore’s future underground community may be?
There is no doubt that the cross-island line will help support the 6.9 million population by the year 2030. However, this same 6.9 million people will also need pristine green spaces for their well-being. In time to come, these remaining primary rainforests may even be gazetted as a world heritage site under UNESCO. Floodgates to further diminish Singapore's remaining bits of nature should hence ever be opened.
And what would Option 3 cost?
Would the entire 50km length need to be deepened, affecting all station depths?
Or could this depth also serve other functions such as civil defence shelters or even connect to the various underground rock caverns where Singapore’s future underground community may be?
There is no doubt that the cross-island line will help support the 6.9 million population by the year 2030. However, this same 6.9 million people will also need pristine green spaces for their well-being. In time to come, these remaining primary rainforests may even be gazetted as a world heritage site under UNESCO. Floodgates to further diminish Singapore's remaining bits of nature should hence ever be opened.
No comments:
Post a Comment